On Thu, 20 Aug 2009 15:06:01 -0700, Julie <Julie.TakeThisOut@discussions.microsoft.com> wrote:
>I have a Gantt chart which has a start date of 8/14. The project will
>actually start later, so I want to move the start date and have all the tasks
>move with it. Is there a way to do this?
Use the mouse to select all the tasks and move them to the new date then
menu Gantt Chart -> Options
and set the new start date.
--
Regards, Paul Herber, Sandrila Ltd.