| Next: I get "Microsoft Office Word has stopped wor.. |
| Author |
Message |
Ruben09 External

Since: Oct 01, 2009 Posts: 2
|
Posted: Thu Oct 01, 2009 11:10 am Post subject: Percentage Archived from groups: microsoft>public>excel>charting (more info?) |
|
|
Hi all,
This is probably a simple question, but can't seem to do it correctly. I'm
trying to create a Pie Chart showing the percentage of hours that have been
completed in a project.
Eg) Total project hours is 3,000 and so far 150 has been completed. I want
the Pie Chart to reflect the 3,000 hours and the slice being the 150. How do
I go about doing this? Thanks in advance.
-Ruben |
|
| Back to top |
|
 |
Luke M External

Since: Jan 08, 2009 Posts: 187
|
Posted: Thu Oct 01, 2009 11:10 am Post subject: RE: Percentage [Login to view extended thread Info.] Archived from groups: per prev. post (more info?) |
|
|
In a2:
Amount completed
in a3:
Amount done
In B1:
3000
In B2:
150
in B3:
=B1-B2
Now, create a pie chart using A2:B3. As you increase the amount of hours
completed, the total value of the pie will remain 3000.
--
Best Regards,
Luke M
*Remember to click "yes" if this post helped you!*
"Ruben09" wrote:
> Hi all,
>
> This is probably a simple question, but can't seem to do it correctly. I'm
> trying to create a Pie Chart showing the percentage of hours that have been
> completed in a project.
>
> Eg) Total project hours is 3,000 and so far 150 has been completed. I want
> the Pie Chart to reflect the 3,000 hours and the slice being the 150. How do
> I go about doing this? Thanks in advance.
> -Ruben
>
> |
|
| Back to top |
|
 |
Ruben09 External

Since: Oct 01, 2009 Posts: 2
|
Posted: Thu Oct 01, 2009 4:10 pm Post subject: RE: Percentage [Login to view extended thread Info.] Archived from groups: per prev. post (more info?) |
|
|
Hi Luke,
is a2=b2?
is a3=b1?
Luke M wrote:
>In a2:
>Amount completed
>in a3:
>Amount done
>
>In B1:
>3000
>In B2:
>150
>in B3:
>=B1-B2
>
>Now, create a pie chart using A2:B3. As you increase the amount of hours
>completed, the total value of the pie will remain 3000.
>> Hi all,
>>
>[quoted text clipped - 6 lines]
>> I go about doing this? Thanks in advance.
>> -Ruben |
|
| Back to top |
|
 |
Gklass External

Since: May 26, 2006 Posts: 14
|
Posted: Fri Oct 02, 2009 7:09 am Post subject: Re: Percentage [Login to view extended thread Info.] Archived from groups: per prev. post (more info?) |
|
|
On Oct 1, 2:29 pm, "Ruben09" <u55173@uwe> wrote:
> Hi Luke,
>
> is a2=b2?
> is a3=b1?
>
> Luke M wrote:
> >In a2:
> >Amount completed
> >in a3:
> >Amount done
>
> >In B1:
> >3000
> >In B2:
> >150
> >in B3:
> >=B1-B2
>
> >Now, create a pie chart using A2:B3. As you increase the amount of hours
> >completed, the total value of the pie will remain 3000.
> >> Hi all,
>
> >[quoted text clipped - 6 lines]
> >> I go about doing this? Thanks in advance.
> >> -Ruben
what he meant was:
A | B
3 Amount completed | 3000
4 Amount done | 150
jsut highlight the four cells and insert the chart |
|
| Back to top |
|
 |
|
|
|
You can post new topics in this forum You can reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum
|
| |
|
|